Collaborating with Jones Brothers Construction on a shared site, Tudor Building Group played a crucial role in the development process. Our involvement commenced with joint efforts in land stripping for both sites. Once Jones Brothers Construction handed over the project to us, Tudor Building Group took charge of mass excavation and utility installations.
On the Greenwood side, Tudor Building Group managed the export of over 200 truckloads of fill dirt, totaling 3,000 cubic yards. Shot rock pads were strategically installed beneath the Sharp townhomes to address specific soil conditions. The rear of both townhome projects necessitated the construction of retaining walls and the incorporation of 11,000 square feet of permeable pavers.
Tudor Building Group took responsibility for all electrical, water, sewer, and storm utilities, ensuring seamless integration with the overall project. Notably, the front of the Sharp townhomes featured bio retention ponds, requiring a cast-in-place footer and excavation after vertical construction had commenced. A total of eight bio retention ponds, each measuring 9×14 feet and 8 feet deep, were installed in front of each home, with meticulous backfilling.
Coordination with Jones Brothers on-site ensured effective management of stormwater discharge. This project serves as a noteworthy example of successful collaboration between our team and another civil team working on a site adjacent to ours.
Tudor Building Group purchased phase 2 of this project from another developer. 21 townhomes were already built in the rear of the property which made it challenging to construct the 21 condos in the front while also maintaining access for the units in the rear.
Considerations went into the development for retail space at this location, such as a coffee shop, but it was determined that the property was better suited to support all residential units. This required Tudor Building Group to go before the city and have the property rezoned.
Once the property was rezoned, our team broke ground on both buildings housing the 21 condos. Both buildings were 3 stories tall with units on each floor. Tudor Building Group worked with architects at Southeast Venture to complete this project. Given the increase in housing demand and overall prices in the Nashville area, Tudor Building Group saw this project as an opportunity to deliver a more affordable product to the Nashville area.
After breaking ground, Tudor Building Group had roughly 1/3 of the units pre-sold and waited until the project was closer to completion before releasing more units. The total build took 14 months due to the tight space restrictions and existing homeowners in the rear of the property. All the units were completed and sold in June 2022. This is a great example of how the Tudor Building Group team can be nimble in complicated scenarios but still deliver a quality product in the end.